Crane Bridge

Lagos, Nigeria

Lagos, Nigeria

  • location

    Lagos, Nigeria

  • year

    2010

  • client

    FLOUR MILLS OF NIGERIA PLC

The project concerns the construction of thirty tons crane bridge for the sugar process factory in Lagos of Nigeria.

Our contract included the design, the construction and the painting procedure of the double-box girder Crane Bridge with thirty tons lifting capacity and span thirty three meters.

The structural design of the double-box girder and the supply of the electrical equipment were taken on by A.B.B. Company. The duration of the crane bridge fabrication was sixty days while it is certified by C.E. The lifting capacity of the specific machine was essential for the installation of the mechanical equipment for the process of the Sugar Refinery Building.